Selective Demolition Projects
Walmart Super center expansions

SCOPE OF WORK: Ascendent LLC has performed the selective demolition required for the conversion to Supercenters at the Shelton, Bonney Lake, South Hill and Spanaway stores. The typical scope of work includes complete removal of the existing customer service areas, general entry and exterior structural masonry walls where the addition is added. All work takes place while the stores had shoppers and employees carrying out there day as usual with out interruption.


Everett Mervyn's Shell & Core Renovation

SCOPE OF WORK: Complete removal of the entire south wall, selective foundation demolition, Remove a freight and passenger elevator, Gutting of the first floor to a clean structure, Saw cutting and removing concrete walls and slabs.

 


Everett Mervyn's South Wall Prior to Demolition
Everett Mervyn's South Wall Prior to Demolition
End of the first day of demolition
End of the first day of demolition
Ascendents 200 size excavator with 45' of working reach
Ascendents 200 size excavator with 45' of working reach
West wall prior to "Toothing" the masonary wall for infill
Completed wall "Toothing"
Kohl's Lacey

SCOPE OF WORK:  To strip the existing 120,000 SF 2 story structure of all interior construction, electrical systems, mechanical and exterior finishes in 4 weeks. Ascendent also performed excavation and grading for the new loading dock and sidewalks.


Exterior before stripping
Exterior after stucco removal
Removing mechanical and electrical systems
Escalator pit removal
Brokk 90 removing a second floor mechanical room slab
Indian Summers Country Club

SCOPE OF WORK: The country club building suffered from water intrusion causing rot and mold through out the structure. Ascendent was contracted to remove various elements of the building including deck membranes, siding, structural stair systems and supporting members. Ascendents Long Reach excavator played a key role in performing serious selective demolition in sensitive areas where disturbing the landscaping or damaging the hard surfaces was not an option.